How to Write a URS for Bespoke Pharmaceutical Equipment

How to write a URS for pharmaceutical equipment, Premech insights

Quick answer. A URS (User Requirement Specification) is the document a pharmaceutical manufacturer writes to define what a piece of equipment must do before it is designed or built. A good URS states the process and performance needs, materials, environment, cleaning, compliance standards, testing and documentation, and describes the requirement rather than the solution.

▍Key takeaways

  • ✓The URS is the starting point for design, quotation and qualification. If a requirement isn’t in it, it is hard to prove later.
  • ✓Most problem specifications are either too vague or too prescriptive.
  • ✓A good URS covers eight areas, from process and materials to documentation and decision ownership.
  • ✓Describe what the equipment must achieve, and let your engineering partner propose how.
  • ✓Involving your engineering partner before the URS is finalised prevents expensive changes later.

Every piece of bespoke pharmaceutical equipment starts with a document. Before anyone draws a frame, specifies a valve or cuts a piece of steel, someone has to write down what the equipment needs to do. In regulated manufacturing, that document is the URS.

A good URS makes everything that follows easier. The design has a clear target, the quotation is based on the same understanding on both sides, and testing at the end has something real to check against. A weak one leads to assumptions, changes and conversations nobody planned for. This is our practical guide, based on the specifications we work from every week.

8
areas every URS should cover
2
ways specifications usually go wrong
10–20
pages is typical for a single skid

What is a URS in pharmaceutical manufacturing?

A User Requirement Specification is a document, written by the equipment user, that sets out what a system or piece of equipment must do. It describes the process, performance, operating environment and standards the equipment must meet. It is usually written by the client, with input from production, engineering, quality and validation.

The URS is also the foundation of equipment qualification. Under EU GMP Annex 15, Design Qualification checks the proposed design against the user requirements, and later tests confirm the finished equipment meets them. We explain how qualification shapes design in our post on GMP and pharmaceutical equipment.

What is the difference between a URS and a functional specification?

The URS describes what the user needs. The Functional Specification, usually written by the supplier, describes how the equipment will meet those needs. In short, the URS says what and why, and the functional specification says how. Keeping the two separate gives your engineering partner room to propose the best solution.

 URSFunctional Specification
AnswersWhat the equipment must do, and whyHow the equipment will do it
Written byThe equipment user (the manufacturer)The supplier, usually your engineering partner
FocusNeeds, performance, environment and complianceThe proposed design solution

Why do so many specifications cause problems?

Most specifications that cause trouble go wrong in one of two ways.

Too vague

Phrases like “suitable for GMP use”, “easy to clean” or “robust construction” appear in a lot of documents. Everyone agrees with them, but nobody agrees what they mean. One person reads “easy to clean” as a polished internal finish and full drainability. Another reads it as a wipe-down frame.

Too prescriptive

The opposite problem is a URS that dictates every bracket position and pipe route before anyone has thought about how the equipment will be built, installed and maintained. This locks in decisions that would be better made with the engineers designing and building it, and can add cost without adding value.

What should a URS include?

For bespoke pharmaceutical equipment, a complete URS should cover these eight areas.

  1. 01Process and performance
    What the equipment does, the product or media it handles, flow rates, pressures, temperatures, capacities and the operating range, including start-up, shutdown and cleaning.
  2. 02Product contact and materials
    Which parts are product contact, the material grade (for example 316L stainless steel), the internal surface finish as a measured value, and seal and elastomer requirements.
  3. 03Installation environment
    Room size, access routes, floor loading, available utilities, cleanroom classification and any hazardous area (ATEX) zoning.
  4. 04Cleaning and maintenance
    Manual or CIP cleaning, drainability, and which components need routine access. Valves, filters and instruments should be reachable without dismantling the equipment.
  5. 05Standards and compliance
    GMP expectations, CE marking, ATEX where it applies, and site or corporate standards. Our guide to what CE marking really means covers this in more depth.
  6. 06Testing and acceptance
    What must be proven at Factory Acceptance Testing (FAT) before the equipment leaves the workshop, and what will be confirmed at Site Acceptance Testing (SAT).
  7. 07Documentation
    The handover package, such as drawings, material certificates, weld records, calibration certificates and manuals, and the format your validation team needs.
  8. 08Ownership
    Who owns each decision on the client side and who approves the design. Delays on bespoke projects very often come from waiting for an answer.
Your guide to writing a URS

To save time on your next project, download our URS guide and template. It sets out all eight areas as ready-to-use tables, with worked examples and checklists, so your team starts every spec from a proven structure, not a blank page.

Download the URS template →

What should you leave out of a URS?

A URS should describe the requirement, not the solution. “The operator must be able to change the filter without tools, from floor level” is a requirement. Specifying the exact position and design of the access frame is a solution, and it is usually better proposed by the people designing it.

✓ A requirement
“The operator must be able to change the filter without tools, from floor level.”
✗ A solution
Specifying the exact position and design of the access frame. Leave this to the people designing it.

Where you have a firm preference, such as an instrument brand used across your site, include it. Where you don’t, leave it open. You will often get a better, simpler or cheaper answer.

When should you involve your engineering partner?

Before the URS is finalised. A short conversation at that stage costs very little and often prevents expensive changes later.

From the workshop

We recently worked with a client who came to us with a URS full of comments and a wish list, but no developed design. Rather than price something that hadn’t been designed, we proposed a short concept design phase first, so the requirements could be tested against a real layout before anyone committed to a final price. It means the quotation, the design and the URS all describe the same piece of equipment.

? Frequently asked questions

What is a URS in pharmaceutical manufacturing?

A User Requirement Specification is a document written by the equipment user that defines what a system must do, including process, performance, materials, environment, cleaning, compliance, testing and documentation requirements. It is the basis for design and qualification.

Who writes the URS?

The end user, usually the pharmaceutical manufacturer. Production, engineering, quality and validation should all contribute. The equipment supplier can review it and suggest improvements, but the requirements belong to the user.

Is a URS a GMP requirement?

EU GMP Annex 15 expects user requirements to be defined and used as the basis for qualification. In practice, any equipment that will be qualified for GMP use should have a URS.

How long should a URS be?

Long enough to be clear and no longer. For a single skid, 10 to 20 pages is common. Length matters less than whether each requirement is specific and testable.

Can a URS change during a project?

Yes, but changes should be controlled, agreed by both sides and reflected in the design, price and programme. Late changes are one of the most common causes of delay.

How Premech can help

Premech designs, fabricates, installs and commissions bespoke equipment for pharmaceutical and highly regulated manufacturers. Reviewing and developing URS documents with clients is a normal part of how we start projects.

Put this blog into practice with our URS guide and template, ready to use on your next equipment project. Download the URS template

If you are writing a URS, or want a second pair of eyes before it goes to tender, contact our team.

Related Projects

Planning a pharmaceutical equipment project for 2027, Premech insights

Planning a Pharmaceutical Equipment Project for 2027

Budgets, lead times, shutdowns and qualification. Seven things to do now if you have a…

Learn More
Premech Engineering ISO 9001:2015 certificate of registration

Premech Achieves ISO 9001:2015 Certification, What It Means for Our Clients

Premech Engineering is now ISO 9001:2015 certified. What it means for pharmaceutical clients, and how…

Learn More
Repair or replace pharmaceutical equipment, a Premech guide to refurbishment

Repair, Refurbish or Replace? Keeping Pharmaceutical Equipment in Service

Should you repair, refurbish, modify or replace worn pharmaceutical equipment? A practical guide to choosing…

Learn More